California Integrated Waste Management Board

 

Reuse Home

Grants

Links and Resources

Programs & Profiles

Events

News

CalMAX

Waste Prevention World

Reuse Assistance Grant Progress Report

City of Napa Reuse Assistance Grant Project
(Part 2: August 1, 2002 to January 31, 2003

 

Project Description

In cooperation with Solano-Napa Builders' Exchange (SNBE), reformed, expanded, and promoted NapaMax (its local materials exchange program) to improve the program's effectiveness. Developed and supported a new, Web-based system (www.napamax.org) with extensive outreach and technical assistance to solicit listings from the entire Solano-Napa region.

The steps required to accomplish their project are as follows:

Task 1: Report to City Council, Obtain Fund Allocation. (3/1/02 to 3/8/02)
The City Waste Reduction/Recycling Coordinator (WRRC) prepared the required reports in late February of 2002. The City Council approved allocation of the requested funds in March 2002. This task is 100 percent complete.

Task 2: Prepare RFP for Software Development, Site Maintenance. (3/1/02 to 3/22/02)
City Recycling Division staff, in cooperation with the City Information Technology (IT) Division staff and Web design consultants, conducted an informal "concept review and comment period" during which it received input from several consultant teams specializing in Web site design. Staff found this step invaluable toward developing a formal scope of work, but, recognized that the work required far more staff time than anticipated, especially the Information time. City staff drafted and revised the RFP from April 2002 through early June 2002. The Recycling Division staff then completed and released the RFP on June 17, 2002. This task is 100 percent complete.

Task 3: Accept and Review Bids, Select Contractor. (4/19/02 to 5/1/02)
Four qualified Web design consulting firms submitted proposals for the Web site development work by the submittal deadline of June 24, 2002. The City will make copies of the proposals available to the CIWMB staff upon request. City staff reviewed the proposals and selected a preferred contractor on Thursday, June 27, 2002. It selected the Napa-based Web site design firm, Genacom, to develop the Web site. This task is 100 percent complete.

Task 4: Prepare Contract for Site Design Set-Up and Maintenance. (5/1/02 to 5/15/02)
The City WRRC, IT staff, and City Attorney's Office worked in cooperation with the consultants to develop the final contract for Web site development. The contract was signed on July 10, 2002. This task is 100 percent complete.

Task 5: Develop, Create, and Test Web Site. (6/15/02 to 3/1/04)
The consultant team has developed several versions of the website to date with format that accommodates an in-depth monitoring system. Genacom also trained five staff members from the City and County on basic HTML to enable them to revise content and listings directly to the website. Genacom refined the site with respect to linkages and subjected it to a battery of tests using sample listings.

Genacom personnel continues to develop descriptive text on several pages of the site and refine language that discloses the type and extent of transaction that has occurred through contacts and "exchanges." The contractor has developed a more e-mail driven format that alerts users to problems, instructions, and notice of potential matching parties. The site continues to evolve and improve with City staff and Genacom working together on this project. The site was open for public use on November 1, 2002. This task is 90 percent complete.

Task 6: Host and Maintain Web Site. (6/15/02 to 3/1/04)
Members of the City IT Division staff analyzed the project to determine the best approach to eventual management of the new website. After reviewing bids and selecting the contractor for website design, the City determined that it could host and maintain the site in-house at less than the budgeted amount of funds. The WRRC determined that the budgeted amount for this task exceeded the need by $6,260.00. After discussing the issue with the CIWMB grant administrator, he prepared a budget revision to reflect a reallocation of the excess funds for the website design work described in Task 1. The revised budget is dated May 6, 2002.

The City IT Division staff started to host and manage the website after the Genacom consultant team had completed testing of the initial testing of the site. The IT staff began work on this task on November 1, 2002. The City has found the work consistent with the existing scope of work for its IT staff and has therefore will arrange with the grant manager to transfer the matching fund expenditure from this task to Task #1 to support additional work by Genacom toward refining and improving elements of the site. This task is 80 percent complete

Tasks 7-9: Tasks of Preparing Listings, Monitoring Use of Site. (6/02 to 3/04)
The City Waste Reduction and Recycling Coordinator began the process of reviewing, approving, and posting listings on November 1, 2002. He will monitor activity and gather data on contacts and exchanges over the next reporting period. The agents responsible for each of these tasks will continue to undertake them between September of 2002 and March of 2004. These tasks are 25 percent complete

Task 10: Develop Design and Layout of Flyers. (Quarterly 5/1/02 to 5/22/02 and 5/1/03 to 5/22/03)
The City Waste Reduction and Recycling Coordinator developed initial design and layout of flyers in-house during November of 2002. He will continue to revise flyer designs over the first year of program implementation. Other versions will be developed in the summer of 2003 and used for ensuing quarters of the project calendar. This task is 20 percent complete.

Tasks 11-15.2, 18-21: Tasks of Preparing, Scheduling, Buying Advertisements. (Quarterly 5/02 to 3/04)
The City WRRC purchased paper and created, folded and delivered flyers to distribution centers. The flyers were addressed to a select group of businesses, agencies and institutions within the project area. Some minor delays in preliminary steps of website design led to the rescheduling of the introductory flyer and Solano-Napa Builders Exchange newsletter advertisements. The result was that flyers and ads were suspended for one quarter. The WRRC therefore doubled the advertisements during the second quarter in an effort to follow substantially the original project timeline and impact public awareness of the new site. Copies of relevant time sheets and receipts are attached to the budget itemization sheet. These tasks are 25 percent complete.

Tasks 16 and 17: Ad and Public Service Announcement Development. (5/02 to 3/04)
The WRRC worked with representatives of the local press and radio to prepare appropriate messages for introducing the new Web site. The introductory messages were run at the beginning of November 2002. Others are scheduled for periodic runs throughout the grant project calendar. These tasks are 25 percent complete.

Tasks 22 and 23: Identify and Analyze Results, Prepare Reports, and Payment Requests. (9/02 to 3/04)
The City hired a consulting firm to monitor and report on the project. The first report was prepared in August of 2002. The company will continue to assist the City to complete Tasks #8, 22, 23, & 24. These tasks are 40 percent complete.

Task 24: Prepare Final Report, Present to CIWMB. (4/04)
The City's consultant and staff assistants will, after compiling and assessing program data, prepare the final report to meet all grant program requirements with the documents prepared by March of 2004. This task has not yet been started.

Anticipated Accomplishments Over the Next Reporting Period:

The City WRRC fully intends to accomplish all tasks according to the detail provided above. The City's main objectives for this project over the next six months are:

  1. Prepare and distribute quarterly advertising.
  2. Refine the look and features of the Web site.
  3. Continue Web site hosting and monitoring.
  4. Attempt to capture more heavy building material listings and use from target generators.

*Permission was obtained from grant recipient to publish project profile.

Back to Top | Progress Report 3

FY 2001/2002 Grant Recipients | Reuse Home

 

Last updated: June 25, 2008


Reuse http://www.ciwmb.ca.gov/Reuse/
Barbara Baker: RAGs@ciwmb.ca.gov (916) 341-6446