|
|
Reuse Assistance Grant Progress Report City of Redding Reuse Assistance Grant Project
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Project DescriptionThe City of Redding used its Reuse Assistance Grant funds to:
The steps required to accomplish their project are as follows: Task 1: Submit City Council Report to Accept Grant, Sign Contract, and
Send to the Department of Conservation. (10/19/00 to 11/30/00) Task 2: Contest to Name the Reuse
Building Drop-Off Area at America Recycles Day Event. (9/30/00 to
11/15/00) The reuse paving expansion will be completed during the first week of June, 2001. The naming contest will be held roughly June 15, 2001 to July 30, 2001. In early June, a draft plan for advertising the naming contest of the expanded reuse drop-off area will be submitted to the Department of Conservation for approval. If the draft is approved by June 12, 2001, then flyers advertising the naming contest could be distributed at the Shasta District Fair, which runs from June 13, 2001 to June 18, 2001. Flyers would also be distributed to the public that attends the reuse auctions on June 15, 2001 and July 6, 2001. Staff will also be manning a recycling/reuse booth at the farmer's market in June. The contest could also be advertised in the July utility newsletter, with the results printed in the Solid Waste Division's September issue of its quarterly newsletter, called the Wastestream. An informal opening of the expanded Reuse Drop-off area will occur at the next auction, which will take place on June 15, 2001. A more formal grand opening could be scheduled in August, when the results of the naming contest can be announced and an advertising campaign run regarding using the expanded reuse drop-off. Task 3: Begin Execution of Grant; Request Bids for Technical
Consultants; and Make Selection of Technical Consultant, Design Fact Sheet. (12/1/00 to 1/30/01) Task 4:
Survey and Design Project Specifications, Prepare Request for Construction Bids.
(2/1/01 to 6/30/01) This task, basically the planning and surveying phase
which resulted in the engineer's RFP specifications and estimate, constituted
the bulk of the grant activity (especially since the paving work took only three
weeks). Enclosed in this report are the specifications for the expansion project
and the ledger detail for public works staff time to complete this task. The
public works staff worked the following hours on this project:
Note : Some hours were worked prior to the grant period (during August and November of 2000). These hours were paid by the City of Redding and are not part of the grant reimbursement. These hours show on this report specifically for the City of Redding to track all staff time spent on this project. Task 4 was completed ahead of schedule, which initially had an end date of June 30, 2001. The survey and design duties were completed when the project specs were completed and published on March 31, 2001. Task
5: Advertise Construction Bid Request. (7/1/01 to 7/30/01) Task 6:
Open Construction Bids. (7/30/01) Task 7:
Prepare Report to City Council to Award Contract and Notify Bidders. (8/1/01 to 8/15/01) Task 8: Sign Contract
Documents and Have Contractor Submit Bonds to Insurance. (8/15/01 to
8/30/01) Task
9: Send Notice to Proceed to Contractor and Begin Construction. (9/1/01 to 9/15/01) Task
10: Construction Process. (9/15/01 to 10/15/01) During the paving project, there were two change orders which increased the cost of construction by $11,336.70 (see Task #11 for more details on the change orders). Following are the initial and revised budgets for this grant project:
Initial Project Budget
Revised Project Budget
Note : There could be some additional adjustments to the budget, once the final numbers come in for Public Works' inspection. As of the writing of this progress report, the hours for inspection were not posted. Reuse/Recycling of Materials During Construction : It should be noted that the City of Redding used roughly 644 tons of recycled highway grindings for the base rock placed under the parking lot expansion. The recycled base rock came from a recent re-paving job on Highway 44. Additionally, 108.5 tons of material removed from parts of the existing curb or parking lot were also recycled. The cement curb and gutters that were removed from the landscaped planter (on the north side of the Admin building), were transported and stockpiled for future grinding and reuse. The cement went to Shea Gravel and the asphalt went to Blaisdell Construction. Task
11: Perform Concurrent Inspections During Construction Process. (9/15/01 to 10/15/01) Regarding construction costs during the inspection phase, there were two change orders made to the project which increased the construction contract by an additional $7,000. The first change order addressed the issue of unsuitable soil, which was discovered during the soil tests: (1) Increased the amount of excavation; (2) Added some soil stabilizing fabric; and (3) Increased the amount of base rock to refill the over-excavation. The second changer order: (1) Lowered the water service under the wall on the north side, which included lowering the landscaping irrigation line that was too high; and (2) Removed and replaced the striping on the south parking lot. Task 12: Issue Notice of Completion,
Go Before City Council, Final Payment to Contractor. (10/15/01 to
11/15/01) Task
13: Advertise Reuse Building Grand Opening to the Public and Distribute Fact
Sheet. (11/15/01 to 11/30/01) Task 14: Perform Project Progress Reports. (12/1/00
to 11/30/01) *Permission was obtained from grant recipient to publish project profile. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Last updated: June 25, 2008 Reuse http://www.ciwmb.ca.gov/Reuse/ Barbara Baker: RAGs@ciwmb.ca.gov (916) 341-6446 |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||