This table illustrates the general tasks and timelines for LEA processing of a full permit. Each task is linked to more detailed instructions, resources, and tools.
Please refer to the entire text of Title 27, Chapter 4, Subchapter 3, Article 3 when using this table.
Note: This page has been updated to reflect the Permit Implementation Regulations effective April 13, 2007. Newly inserted text is shown with a shaded background.
| LEA Full Permit Process Tasks | Time Lines (Calendar Days) | |
|---|---|---|
|
Prior to submittal of application |
|
|
30 Days to accept or reject application package. |
60 Days to hold informational meeting for revised and new permits.
|
|
||
|
Note 1: For new and revised full permits, the LEA must hold a informational
meeting within 60
days of receiving an application, in addition to making a completeness
determination within 30 days. Note 2: The informational meeting must be held after the LEA has made its' completeness determination. Note 3: Modified permits require the LEA to notice the LEA's preliminary determination to modify the permit. Note 4: For new and revised full permit applications, the EA is required to notice the governing body of the local jurisdiction where the facility is located and the appropriate State Assembly Member and State Senator of an upcoming informational meeting. |
|
|
||
|
|
120 days PRC Section 44008 |
|
Board has 60 days to concur or object PRC Section 44009. |
|
|
||
|
||
|
Until permit is revoked or site is closed. |
||
| At least once every 5 years after issuance until closure. | ||
|
As changes occur or are proposed at the facility. |
||
Note: This page has been updated to reflect Assembly Bill 1497 (effective on January 1, 2004). See the all-LEA email providing interim guidance on implementing the provisions of AB 1479.