Construction/Demolition and Inert Debris Tools and Resources Regulations 101 Presentation |
||||||||||
|
The following is a presentation on the construction and demolition waste regulations adopted by the California Integrated Waste Management Board in 2003. Topics covered include background, construction and demolition debris characteristics, the regulations and the aftermath. Background: CIWMB Vision & MissionOur Vision. A sustainable California, where our unique natural environment is preserved for future generations. Our Mission. To reduce waste, promote the management of all materials to their highest and best use, and protect public health and safety and the environment, in partnership with all Californians. The Objective. Section 17380.1 Purpose. (a) It is the board’s intent in adopting this Article to encourage the recycling and reuse of C&D debris and inert debris that may otherwise be disposed in a solid waste disposal facility. Why Do We Have the Tiers in the First Place?To Offer Something:
Examples:
Also:
Why Do Operators Like the Registration Tier?
What Do The C&D Processing Regs Do?They:
What the Regs Created
Milestones in the Regulatory Process
C&D Debris Characteristics 2003 Waste Characterization Study2003 MSW Components
Main Complaints: Odor, Vectors, Noise, Traffic, and Dust What are the Environmental Indicators for C&D and MSW Processing Facilities?
C&D Composition 2003C&D Disposal Now at 21.7%
Main Complaints: Noise, Traffic, & Dust C&D Generation Forecasts
Correlation for Increase in C&D Generation? CDI Recycling CentersNo Tonnage Limit No State Minimum Standards Storage Limits: Storage Plan May Be Required
Tests:
Inert (Type A) Debris Recycling CentersNo Tonnage Limit No State Minimum Standards Storage Limits: Storage Plan May Be Required
Tests:
Differences in Regulatory Oversight
What Areas Need Research Prior to Re-evaluating the Regs for Higher Permit Tier Thresholds?
Questions and AnswersConstruction Work sites that recycle their own C&D are not subject to the CDI processing requirements. But what if the activity accepts off-site debris for recycling into a new structure? Choices:
Answer: The Regs allow the importation and use of C&D Debris. But, it Can’t remain at the site after the construction work is completed. Reason: This reg prevents processing disguised as construction activities. Is on-site storage of inert manufacturing debris regulated by the CIWMB? Choices:
Answer: Manufacturing is not regulated by the Board. Board regulates sites that receive, store, handle, transfer or process C&D debris and inert debris. Regional Water Board may have authority. If a recycling center exceeds storage limits does it get bumped up to a permitted facility? Choices:
Answer: No. The site could get a storage extension, or it can be issued an order to cease the illegal disposal. How do I determine how long debris has been stored? Choices
Answer: Operators are required to keep adequate records. Inspect incoming and outgoing records to determine the storage time length. Bottom of a pile "last in, first out” rule of pile processing even though records reflect a turn over of debris within the regulated storage limits. As long as there are no public health, safety and environmental concerns LEA focus should be residual removal, putrescibles, and whether there is MSW on site. The key is that storage limit non-compliance means disposal – LEA can take action for illegal disposal. If a site exceeds the storage time limits is the debris considered to be disposed? Choices
Answer: Yes and no. Yes, It is considered disposal so that the LEA can take enforcement action. No. Because the material is disposed only when it reached its final destination of placement in a permitted disposal facility. But not if routed to a processing center that recycles it, or it is allowable fill at an inert debris engineered fill operation. Can an operator lawfully exceed the total amount of material allowed on site? Choices:
Answer: No. The Amount is determined by max tpd times 30 (days) or, the site could apply for a full SWF permit under Article 6.0 Do I have to accept a deficient Operation Plan? Choices:
Answer:
No.
The EA Notification can be rejected if the plan is not complete and accurate. What commingled debris can be accepted at a CDI recycling center? Choices:
Answer: Recycling centers must have debris separated at the point of generation. Regs allow commingling in a single container of cardboard, wood and metal. What is "serial processing”? Should I be concerned with it? Choices:
Answer: Serial processing is when a site records less than 10% for disposal, yet some materials require further processing at a second location. Remedy - Check the recycling rate at the 2nd location and have the operator put it In writing! What differs between the terms: "C&D waste” and "C&D debris”? Choices:
Answer: C&D waste can be all the waste generated at a C&D site. Debris is a subset, if it is the portion that contains recyclables and less than 1% putrescible material. What are the main differences between the C&D regulations - the Transfer/Processing regulations & the Compostable Materials regulations? Choices:
Answer: The Debris Limitations:
The Source must be from "Construction Work” A home remodel roll-off bin contains C&D debris but also a neighbors garage items like toys, weights, a surfboard, and clothes. Are all these materials considered to be C&D debris? Choices:
Answer: No, the material doesn’t meet the definition of C&D debris because some of the material does not result from "construction work” as defined in 17381(g) and the other materials do not meet the definition of C&D debris or inert debris. A storage shed made of stucco is demolished along with the contents of the storage shed, i.e.; lawnmower, rakes, lawn chairs, bikes, and shovels. Is this material considered to be C&D debris? Choices:
Answer: Yes, because it comes directly from construction work - demolition of a shed. and does not include prohibited material (Arguably, the contents of the shed, which are typical items found in a storage shed, could be described as "equipment” and "furnishings,” as described at 14 CCR 17381(e)(1)(A).) Are C&D processing sites at landfills regulated under this Article? Choices:
Answer: The site should be included as a unit within the landfill permit. Existing sites must amend their RDSI promptly. If it is a new activity – review for CEQA. If not included as a unit w/in the landfill permit, then it will need to be permitted separately. Acceptance of what waste stream commonly kicks CDI processing sites over to the transfer processing facility regs? Choices:
Answer: Any non-C&D Debris – but mostly Greenwaste. C&D is a drier material than urban green waste and it poses lesser impacts than greenwaste. Why is greenwaste prohibited at CDI processing sites when most of the operators would like to accept the material? What if the greenwaste is part of a demolition project? Answer: Landscape debris is not C&D debris. Flies and odors are produced along with greenwaste. It is subject to Article 6.0 through 6.35 or the Compostable Materials regulations. Landscape debris can only be commingled if it results from construction work. (Landscaping material bulldozed along with a building and/or parking lot.) Note: there is still a 48 hour removal requirement of putrescible material in force. An Operator can accept both materials under a transfer/processing permit. Is gypsum wallboard inert? Is it putrescible? Choices:
Answer:
Generally speaking, mineral gypsum (calcium sulfate) is an inert material. Under anaerobic conditions with moisture, gypsum wallboard can be putrescible (Putrescible Wastes” means solid wastes that are capable of being decomposed by micro-organisms with sufficient rapidity as to cause nuisances because of odors, vectors, gases or other offensive conditions, and include materials such as, but not limited to food wastes, offal and dead animals. The EA shall determine on a case-by-case basis whether or not a site is handling putrescible wastes.) If an LEA finds wallboard at the site is putrescing – then it is putrescible! Is neighborhood clean up debris, beach, river and marsh cleanup debris, & Cal Trans road side pick-up bags considered to be C&D? What about street sweeping debris, is it inert? Choices:
Answer: These wastes are not related to construction work. Neighborhood cleanup debris typically consists of appliances, furniture, mattresses and box springs, tires, BBQ grills and other outdoor items, bicycles, lumber, PVC pipe, and appliances. Beach, river and marsh clean up debris typically consists of wood, glass, bottles, cans, plastic, metal, fiber, fabric, cigarette butts, monofilament fishing line, plastic sheeting, tires and Styrofoam. Street Sweepings don’t meet the definition of inert debris. Street sweepings are materials such as sand, salt, grit, and organic material removed from city streets, parking lots and sidewalks to prevent these materials from being washed into storm sewers and surface waters, and to improve the appearance of public roadways. Inert debris does not contain soluble pollutants at concentration in excess of water quality objectives and do not contain significant quantities of decomposable waste. Is it ever acceptable to have construction contractor office recyclables mixed with C&D debris? Choices:
Answer:
Yes, when its commingled with C&D.
Otherwise, it’s transfer processing debris. Does source separated material count toward a CDI debris processing facility’s total tonnage? Choices:
Answer: Yes, C&D debris and inert debris are specific types of solid waste per section 17380. All material received at the site factors into the total tonnage calculation. So, everything through the gate counts as tpd. Do CDI processing facilities have to be identified in the NDFE before the LEA can process the paperwork? Choices:
Answer:
Yes, the NDFE finding is required in the application for permits, (not for EA
notifications. What is "C&D Like” and why should I be interested? Choices:
Answer: Because if the debris does not come from C&D: It must be from manufacturing, or generally similar and not produce ANY residual material and NO putrescibles or it can be Wood-overs from cabinet manufacturing Are garage clean-outs C&D debris? Choices:
Answer: Garage clean-outs are usually junk hauls. The LEA can check to see if the site advertises acceptance of garage clean-out debris. (Unless the recycling results in no residual material, or the materials came from a home remodeling project.) What about self-hauls, can they be considered to be C&D loads? Choices:
Answer: Yes. Determine whether the debris come from a C&D site or home remodel. Certainly, a (DIY) home remodel bin is sufficiently akin to C&D if limited to C&D. Remember - No general household garbage. Do I need an approved Fire Plan for a C&D Debris Processing Facility operating under a Transfer/Processing Permit? Choices:
Answer: It is up to the LEA. Article 6.0 does not require a fire plan at this time. However, the LEA can require the operator in the permit to include a fire plan or require the fire plan be included in the RFI. Who determines whether multiple activities should be regulated separately or all under one permit? Choices:
Answer: The LEA does. Pursuant to: Section 17383.1 multiple wood debris chipping and grinding activities. See LEA Advisory #39 - Issuance of Multiple Permits. What material storage time limits do I apply to multiple facilities or activities at one facility? Choices:
Answer: For commingled material – CDI debris processing storage times of 15 days unprocessed / 12 mo. processed apply. A processor with 3 distinct debris streams should have storage times consistent with the debris stream such as:
What is the difference between Inert Debris Recycling Sites and Inert Debris Processing Operations? Choices:
Answer: Inert debris processing operations have over 10% residual waste. Inert debris recycling sites have under 10% residual waste. Is the Crushing and Grinding of Inert Debris Regulated? Choices:
Answer: No, source separated inert debris can be crushed and ground at a CDI recycling center as long as it was not commingled with any other CDI material & has <10% fesidual. Is Inert Debris Dumped by the Side of the Road Regulated by the C&D Regs? Choices:
Answer: It depends. It could be determined to be illegal disposal & destined for clean up, or it could have storage standards of the CDI processing regulations applied. Material used in construction of roads, etc. is Excluded from the Regulations. What is Type B Debris? Isn’t it over-kill to regulate some very benign Type B debris in this manner? Choices:
Answer: It is waste determined to be inert by the RWQCB but excluded type A inert debris. Examples are:
However, per section 17388(k)(1) The Board, upon consultation with the SWRCB will determine on a case-by-case basis whether materials not listed in the regs qualify as Type A inert debris. The Board with the SWRCB will consider statewide & site-specific factors in making this determination. Can an inert debris recycler accept C&D wood if the amount is less than 10% residual per section 17381.1(b)(1)? Choices:
Answer: The regs state only type A inert debris can be accepted. However, wood can inadvertently be commingled with inert debris as in the case of concrete forms thrown into an inert debris bin. The operator has the burden of proof to show that only type A inert debris is accepted. The LEA can assess this on a case-by-case basis taking into consideration the impacts to public health, safety and the environment. Is mining waste and gangue considered to be inert debris? Choices:
Answer: Mining waste is separated into three categories by state water board:
Gangue is a subset of mining waste. So, If it is determined to be inert, it could be considered Type B debris. Note: gangue RETURNED to a mine as part of reclamation material sent or received from off-site, could be subject to the regulations. (Gangue - sand, rock, and other impurities surrounding the mineral of interest in an ore) What about Ash – is it inert debris? Choices:
Answer: Ash is also separated into 3 categories by the State water board:
If the ash is determined to be an inert debris by the RWQCB then it would be type B debris & can be regulated under Article 5.8 - nonhazardous ash regs. Do sites that recycle inert debris have to meet storage limits? Choices:
Answer: Not if it’s a "material production facility”, which is most commonly an aggregate operation, a hot mix asphalt plant, or Portland cement manufacturing facility. I’ve heard that inert debris stored at public agencies must meet storage time limits. Is this true? Choices:
Answer: Yes, but the LEA can allow an extension of the Storage Time Limits. What possible hazards may exist in C&D debris?
Aren’t there health and environmental impacts associated with the grinding of lead painted wood and concrete? Choices:
Answer: Yes, but hazardous materials must NOT be accepted at a SWF & must be prevented through signage, customer education & load checking, or, if discovered, it must be separated from other debris. Should we be Concerned with Friable Asbestos at C&D Processing Sites? Choices:
Answer:
Yes, Again - Hazardous materials must NOT be accepted at a SWF and C&D Wood Debris Chipping and Grinding Operations and FacilitiesWhat are the Main Differences Between the C&D Chip & Grind Regulations & the Compostable Materials Chip & Grind Regulations? Choices:
Answer:
The C&D chip & grind regs do not allow compostable material.
The compostable materials regs allow C&D wood but do not allow other C&D debris
like asphalt roofing shingles. Could C&D wood debris chipping and grinding require application of the Compostable Materials requirements? Choices:
Answer: Yes, if it generates temperatures of at least 122 degrees Fahrenheit. If this is the case, it’s Regulated as a compostable material handling operation or facility, per Chapter 3.1 Is pallet grinding a regulated activity by the LEA? Choices:
Answer: If it is making wood mulch as defined in the C&D wood debris chipping and grinding requirements. What commonly sold wood must never be received at a C&D site? Choices:
Answer: Chromated copper arsenate (CCA) treaated wood. Section 17383.3. (c)(4) states that the operator shall take adequate measures through signage, training, load checking, detection systems, and/or chemical analysis to avoid incorporating any CCA pressure treated wood and lead based painted materials into C&D mulch. Such contaminated feedstock shall be stored in a designated area for proper handling and disposition. Can creosote treated railroad ties be chipped and ground for C&D mulch? Choices:
Answer: No, According to recent legislation, creosote treated railroad ties can be considered to be hazardous waste when used in certain circumstances. What’s Next?
C&D Debris Disposal Regulations 101Topics
Phase II Disposal RegulationsBoard approval on September 17, 2003. Approved by OAL on December 26, 2003. 60 day delay in implementation. Effective Date In February 24, 2004 Inert Debris Characteristics"Inert Debris" means solid waste and recyclable materials that are source separated or separated for reuse and do not contain hazardous waste (as defined in CCR, Title 22, section 66261.3 et. seq.) or soluble pollutants at concentrations in excess of applicable water quality. Inert debris may not contain any putrescible wastes. Gravel, rock, soil, sand and similar materials, whether processed or not, that have never been used in connection with any structure, development, grading or other similar human purpose, or that are uncontaminated, are not inert debris. Such materials may be commingled with inert debris. Inert Debris Type A "Type A Inert debris" includes but is not limited to concrete (including fiberglass or steel reinforcing bar embedded in the concrete), fully cured asphalt, crushed glass, fiberglass, asphalt or fiberglass roofing shingles, brick, slag, ceramics, plaster, clay and clay products. Type A inert debris is waste that does not contain soluble pollutants at concentrations in excess of water quality objectives and has not been treated in order to reduce pollutants. The board, upon consultation with the State Water Resources Control Board, will determine on a case by case basis whether materials not listed in this subdivision qualify as Type A inert debris. The board and the State Water Resources Control Board may consider statewide and site-specific factors in making this determination. Inert Debris Type B "Type B inert debris" is solid waste that is specifically determined to be inert by the applicable RWQCB, such as treated industrial wastes and de-watered bentonite-based drilling mud, but excluding Type A inert debris. Phase II Tier PlacementInert Debris Engineered Fill Operation = EA Notification The RegulationsInert Debris Engineered Fill Operations
Inert Type A Debris Disposal Facility
Questions & AnswersIs the < 1% residual amount at an inert debris engineered fill (IDEF) operation by weight or volume? Choices:
Answer: No amount of residual material or putrescible material is allowed for placement at an IDEF. Is there a limit on the amount of TPD that can be placed at an IDEF operation? Choices:
Answer:
No.
Section 17388.3 does not limit the max daily tonnage for an IDEF operation. What is the difference between C&D debris and inert debris – aren’t they the same? Choices:
Answer: No, not in these regulations. Inert debris can come from any source whereas C&D debris comes only from C&D sites. Also, inert debris does not contain materials that are compostable or degradable. Why aren’t IDEF operations allowed to accept all Inert Type A debris? Choices:
Answer: Because some plastics are degradable and some type A inert debris have a BTU value to them and can burn. So, although the SWRCB may consider all type A debris to be inert, the CIWMB considers combustibility issues with disposal of this material and only allows a subset of Type A debris: fully cured asphalt, uncontaminated concrete, crushed glass, brick, ceramics, clay & clay products which may be mixed with rock and soil. Does Subsection 17388.2(a)(6) Exclusion For Use By Government Agencies apply to operators that accept and dispose of inert debris from various government projects? Choices:
Answer:No, this subsection only excludes the "use” of inert debris in "connection” with road building/repair bridge & roadway work, levee work, & flood control projects by government agencies.An LEA should not use this section to exclude disposal operations because the material is generated by a government agency. Contact:
|
|||||||||||
|
Last updated: November 01, 2007 LEA Training http://www.ciwmb.ca.gov/LEATraining/ Melissa Hoover-Hartwick: mhoover@ciwmb.ca.gov (916) 341-6813 |
|||||||||||