Construction/Demolition and Inert Debris Permitting
Permit Phase-In Process
|
|
Permit CDI Timelines
- 8/9/03 effective date of the regulations and begins the time clock for
having activities permitted
- EA determination must be made within 30 to 90 days of the effective
date of the regulations - notify operators between
9/9/03 and 11/7/03
- EA notification must be granted within 30 days of EA determination
- Registration permit issued within 60 days of EA determination
- Temporary registration permit issued within 60 days of EA
determination- apply for a Full Permit within 1 year from EA determination
- Full permit issued within 180 days of EA determination
- Temporary registration permit initially good for up to 2 years while
obtaining a full permit
- Temporary permit can be extended for an additional 3 years if operator
is proceeding to obtain a full permit in good faith and due diligence, but is delayed because of
reasons beyond the operator’s control
|
|