On September 1, 1996, a final summary was made of the amounts of wood recovered from Building 901.
The information is contained in the table below.
| Member/Species |
Dimension |
Volume |
Volume Recovered
(% Recovered)
|
| Roof Plank (T&G)/Pine-Fir |
1" x 8" x 10'-15'
1" x 12" x 10'-15' |
4800 bf
4800 bf |
1200 bf (25%)
2400 bf (50%) |
| Wall Plank /Ponderosa Pine |
1" x 10" x 6'-10'
1" x 12" x 6'-16' |
1200 bf
2600 bf |
1100 bf (90%)
2500 bf (95%) |
| LDF Wall, Peak Liner/Unk. |
1" x 4' x 8' |
300 sheets |
0 (0%) |
| Firring/Port Orford Cedar |
1" x 2" x 6'-10' |
200 bf |
10 bf (5%) |
| Interior Ply/ Doug Fir |
0.25" x 4 'x 8'
0.5" x 4 'x 8' |
55 sheets
8 sheets |
52 sheets (95%)
8 sheets (100%) |
| Non-Struct. Framing/Doug Fir |
2" x 4" x 8'-12' |
500 bf |
450 bf (90%) |
| Ridge, Purlin /Doug Fir |
2" x 10" x 20' |
2350 bf |
1700 bf (70%) |
| Rafter/Doug Fir |
2" x 8" x 14'
2" x 8" x 20' |
2800 bf
4000 bf |
2670 bf (95%)
3800 bf (95%) |
| Cross-tie, Stud/ Doug Fir |
2" x 8" x 16' |
2000 bf |
1950 bf (95%) |
| Post/Doug Fir |
6" x 6" x 13'
6" x 6" x 16' |
1400 bf
1700 bf |
1400 bf (100%)
1680 bf (99%) |
| Brace/Doug Fir |
2" x 6" x 12' |
3000 bf |
2700 bf (90%) |
| Stud, Ceiling Joist/Fir-Pine |
2" x 6" x 10' |
1500 bf |
1350 bf (90%) |
| Stud,Ceiling Joist/Redwood |
2" x 6" x 8' |
600 bf |
540 bf (90%) |
| Siding/Redwood |
1" x 6" x 6'-20' |
1600 bf |
1200 bf (75%) |
| Ext. Deck,Joist, Facia/ S-P-F |
2" x 4" x 6'-14'
2" x 12" x 14' |
500 bf
1100 bf |
0 bf (0%)
1080 bf (99%) |
| Flooring (T&G)/ Doug Fir |
1" x 4" x 3' |
45 bf |
45 bf (100%) |
| Flooring(T&G)/ Port Orford Cedar |
2" x 8" x 12'-24' |
15,600 bf |
15,500 bf (99%) |
| Floor Joist/ Doug Fir |
2" x 12" x 14' |
21,400 bf |
21,300 bf (99%) |
| Sill/ Pine |
2" x 6" x 14' |
800 bf |
720 bf (90%) |
| Total |
75,295 bf |
65,295 bf (87%) |
Information contained in Table 1 was provided by San Francisco Community
Recyclers and Wood Resource Efficiency Network.